Removal of Residue in the IBC

-IBC are  segregated into various types and sizes.

-Residues in the IBC undergo our suction system to remove leftover chemical residues.


High Pressure Semi Auto Flushing on IBC 

-Contaminated IBC are flushed and washed under high pressure water jet system to clean up the IBC


Final Preparation of the Reconditioned IBC

-Washed IBC are dried and clean up to pristine condition.

-Damaged or malfunctioning parts will be replaced.


Quality Conformance Check

-All the IBC parts are checked to ensure it is in good working condition. 





Segregation of HDPE Drums & Smaller Carboys

-Various types of drums and carboys are segregated in accordance with their chemical residues to prevent unneccessary chemical reactions.


Removal of Residue in the Drum & Carboys

-Drums are  segregated into various types and sizes.

-Residues of the same types in the drums undergo our suction system to remove leftover chemical residues.


High Pressure Water Jet Exterior Cleaning

-External portion of the HDPE Drums / carboys are flushed and jetted clean with high pressured clean water jet spray.


High Powered Flushing System

-Internal portion of the drums and carboys are flushed 360 degree with clean water at high pressure .


Air Dry HDPE Drums

-Reconditioned HDPE Drums and carboys are air dried and stacked in accordance to their capacity and types, ready for resale.


drum
drum
drum
drum

Removal of Residue in the Drum

-Drums are  segregated into various types and sizes.

-Residues of the same types in the drums undergo our suction system to remove leftover chemical residues.


Pre-Wash

-Drums are rinsed in our cleaning tanks to further remove any stubborn stains.


Drums Conformity Preparation

-Dented Drums are blow back into its original cylinderical shape.

-Leak Test were performed to check on any possible leakages.


Caustic Solution Hot Wash

-Drums are flushed both internally & externally with degreasing solutions at high temperature for deep clean.


Anti-Rust Solution Rinsing

-Drums are rinsed  with a neutral corrosion inhabitor solution to prevent rusting. 


After Wash QC Check

-Clean Drums undergo 1st round of quality conformance check.


Removal of Excess Water

-Washed Drums are passed through our water suction station to remove all excessive waters within. 


Spray Painting

-Drums are passed into our spray paint booth to undergo recoating of fresh paint work.


Oven Baking

-Newly coated drums baked at 150 Degree Celcius for approximately 20 to 30 minutes to ensure lasting and shiny paintwork.


Final Inspection and Closure of Screw Caps

-Reconditioned Drums are undergo 2nd round inspection conformance check, followed by tightening the screw caps.